We are targeted to open in April of 2016
HVAC units have been installed
Grease trap has been installed
Wall framing will be complete on Tuesday of this week
Water line ruff in complete in existing walls and will be complete in new walls Wednesday of this week
Gas line install starts Monday
Electric ruff in will be complete next week
New electric service starts next week

JR has started marketing and hiring will start soon.